notifications
category
Quantitative Aptitude

Quantitative Aptitude Topics

Undergraduate level — Quantitative Aptitude

topic
5
Topics
quiz
250
Question bank
star
500
Total marks
description
0
Materials

Choose question count and time — session stays in your browser only.

filter_alt Topics

lock

Percentages & Ratios

Locked · Complete previous topics to unlock

lock

Time & Work

Locked · Complete previous topics to unlock

lock

Profit & Loss

Locked · Complete previous topics to unlock

lock

Geometry

Locked · Complete previous topics to unlock

lock

Data Interpretation

Locked · Complete previous topics to unlock

quiz Questions

help

Q91

A completes a work in 19 days and B in 23 days. In how many days will they finish together?

1 · 2 marks · MCQ

A.

10.4

B.

21

C.

19

D.

23

Explanation

Combined rate = 1/19+1/23; Time = 10.4 days.

help

Q92

A completes a work in 6 days and B in 15 days. In how many days will they finish together?

2 · 2 marks · MCQ

A.

4.3

B.

10.5

C.

15

D.

6

Explanation

Combined rate = 1/6+1/15; Time = 4.3 days.

help

Q93

A completes a work in 19 days and B in 6 days. In how many days will they finish together?

3 · 2 marks · MCQ

A.

4.6

B.

12.5

C.

6

D.

19

Explanation

Combined rate = 1/19+1/6; Time = 4.6 days.

help

Q94

A completes a work in 14 days and B in 9 days. In how many days will they finish together?

4 · 2 marks · MCQ

A.

14

B.

11.5

C.

5.5

D.

9

Explanation

Combined rate = 1/14+1/9; Time = 5.5 days.

help

Q95

A completes a work in 11 days and B in 19 days. In how many days will they finish together?

5 · 2 marks · MCQ

A.

19

B.

15

C.

7

D.

11

Explanation

Combined rate = 1/11+1/19; Time = 7 days.

help

Q96

A completes a work in 14 days and B in 19 days. In how many days will they finish together?

1 · 2 marks · MCQ

A.

8.1

B.

16.5

C.

19

D.

14

Explanation

Combined rate = 1/14+1/19; Time = 8.1 days.

help

Q97

Time & Work — A completes a work in 7 days and B in 15 days. In how many days will they finish together?

2 · 2 marks · MCQ

A.

4.8

B.

11

C.

7

D.

15

Explanation

Combined rate = 1/7+1/15; Time = 4.8 days.

help

Q98

A completes a work in 23 days and B in 23 days. In how many days will they finish together?

3 · 2 marks · MCQ

A.

11.5

B.

598

C.

23

D.

550

Explanation

Combined rate = 1/23+1/23; Time = 11.5 days.

help

Q99

A completes a work in 10 days and B in 10 days. In how many days will they finish together?

4 · 2 marks · MCQ

A.

5

B.

704

C.

931

D.

10

Explanation

Combined rate = 1/10+1/10; Time = 5 days.

help

Q100

A completes a work in 22 days and B in 17 days. In how many days will they finish together?

5 · 2 marks · MCQ

A.

22

B.

19.5

C.

9.6

D.

17

Explanation

Combined rate = 1/22+1/17; Time = 9.6 days.