notifications
category
Quantitative Aptitude

Quantitative Aptitude Topics

Undergraduate level — Quantitative Aptitude

topic
5
Topics
quiz
250
Question bank
star
500
Total marks
description
0
Materials

Choose question count and time — session stays in your browser only.

filter_alt Topics

lock

Percentages & Ratios

Locked · Complete previous topics to unlock

lock

Time & Work

Locked · Complete previous topics to unlock

lock

Profit & Loss

Locked · Complete previous topics to unlock

lock

Geometry

Locked · Complete previous topics to unlock

lock

Data Interpretation

Locked · Complete previous topics to unlock

quiz Questions

help

Q51

A completes a work in 23 days and B in 16 days. In how many days will they finish together?

1 · 2 marks · MCQ

A.

16

B.

23

C.

9.4

D.

19.5

Explanation

Combined rate = 1/23+1/16; Time = 9.4 days.

help

Q52

A completes a work in 6 days and B in 21 days. In how many days will they finish together?

2 · 2 marks · MCQ

A.

21

B.

13.5

C.

6

D.

4.7

Explanation

Combined rate = 1/6+1/21; Time = 4.7 days.

help

Q53

A completes a work in 7 days and B in 15 days. In how many days will they finish together?

3 · 2 marks · MCQ

A.

4.8

B.

11

C.

15

D.

7

Explanation

Combined rate = 1/7+1/15; Time = 4.8 days.

help

Q54

A completes a work in 24 days and B in 19 days. In how many days will they finish together?

4 · 2 marks · MCQ

A.

21.5

B.

10.6

C.

19

D.

24

Explanation

Combined rate = 1/24+1/19; Time = 10.6 days.

help

Q55

A completes a work in 17 days and B in 12 days. In how many days will they finish together?

5 · 2 marks · MCQ

A.

7

B.

14.5

C.

17

D.

12

Explanation

Combined rate = 1/17+1/12; Time = 7 days.

help

Q56

A completes a work in 18 days and B in 9 days. In how many days will they finish together?

1 · 2 marks · MCQ

A.

18

B.

6

C.

9

D.

13.5

Explanation

Combined rate = 1/18+1/9; Time = 6 days.

help

Q57

A completes a work in 13 days and B in 9 days. In how many days will they finish together?

2 · 2 marks · MCQ

A.

5.3

B.

11

C.

9

D.

13

Explanation

Combined rate = 1/13+1/9; Time = 5.3 days.

help

Q58

A completes a work in 14 days and B in 23 days. In how many days will they finish together?

3 · 2 marks · MCQ

A.

23

B.

18.5

C.

14

D.

8.7

Explanation

Combined rate = 1/14+1/23; Time = 8.7 days.

help

Q59

A completes a work in 13 days and B in 16 days. In how many days will they finish together?

4 · 2 marks · MCQ

A.

14.5

B.

7.2

C.

13

D.

16

Explanation

Combined rate = 1/13+1/16; Time = 7.2 days.

help

Q60

A completes a work in 12 days and B in 14 days. In how many days will they finish together?

5 · 2 marks · MCQ

A.

14

B.

13

C.

6.5

D.

12

Explanation

Combined rate = 1/12+1/14; Time = 6.5 days.